Construction intelligence · public records
What real projects cost, from the public record.
91,977 project records from government awards, airport grants, highway bids and mine studies filed with the SEC, covering 20 countries. Each one links to where it was published. No commercial cost database is used.
Look up a project
Describe the asset with its size: floor area for a building (sq ft or m2), miles or km for a road, throughput for a mine (t/d or Mt/yr), MW for a power plant, length and width for a runway. You get the records behind it, the range they support, and how that range scored on records it had not seen.
Records by asset type
These project records are part of the 239,758 public cost records on file. Costs are moved to today’s prices with BLS PPI, New school building construction (PCU236222236222) for buildings and BLS PPI, Net inputs to other nonresidential construction, goods (WPUIP2312301) for civil works, mines and power (2026-10).
| Asset type | Records |
|---|---|
| Highway pay items (Oregon and Hawaii bids) | 42,400 |
| Roads and bridges | 5,326 |
| Other buildings | 4,310 |
| Water, dams and ports | 4,305 |
| Other works | 4,209 |
| Hospitals and clinics | 2,058 |
| Airports (other works) | 1,881 |
| Offices | 1,860 |
| Utilities and pipelines | 1,689 |
| Housing and barracks | 1,128 |
| Oil and gas pipelines | 1,081 |
| Industrial buildings | 874 |
| Parks, sport and recreation | 830 |
| Warehouses and storage | 659 |
| Mines | 458 |
| Schools and training | 451 |
| Airport runways (per sq yd) | 411 |
| Power and energy works | 252 |
| Laboratories | 106 |
| Rail | 91 |
| LNG plants and terminals | 7 |
| Gas processing plants | 4 |
| Refineries and renewable fuels | 2 |
| Petrochemical plants | 1 |
| Airport grants (other AIP work) | 17,584 |
| Power generation, EIA published averages (not counted as records) | 547 |
Records by country
Where the work is. U.S. federal awards for work outside the United States are shown as one group; mine studies cover projects worldwide.
United States 70,063 · US federal award, overseas 2,680 · Singapore 1,241 · Canada 74 · Mexico 26 · Chile 9 · Argentina 9 · Brazil 6 · Australia 4 · Ghana 4 · Peru 3 · Guatemala 3 · Ecuador 3 · Senegal 2 · Colombia 2 · Burkina Faso 2 · Tanzania 2 · Mali 1 · Greece 1 · Namibia 1 · Romania 1
Oil, gas, LNG and pipelines
1,070 U.S. natural gas pipeline projects with a reported cost, miles and diameter, from the EIA pipeline projects workbook, give a cost per inch-mile. 25 LNG, refinery, gas processing, petrochemical and liquids pipeline project costs were read by hand from company announcements filed with the SEC; each is one project’s stated budget or estimate, not a final cost. No government publishes refinery, LNG or offshore field costs project by project, so this set stays small and is shown as comparables.
| Project | Type | Country | Capacity | Stated cost | Today, USD | Filed |
|---|---|---|---|---|---|---|
| Birch-to-Taylor Expansion (95 km)Pembina Pipeline · capital budget | Oil and gas pipelines | Canada | 120,000 bpd | CAD 310M | $223M | 2026-11-05 |
| Fox Creek-to-Namao ExpansionPembina Pipeline · capital budget | Oil and gas pipelines | Canada | 70,000 bpd | CAD 200M | $159M | 2026-02-27 |
| Cedar LNG (floating)Pembina Pipeline · Class III estimate, gross; excludes ~US$0.6B interest during construction and transaction costs | LNG plants and terminals | Canada | 3.3 Mtpa | USD 3,400M | $3,754M | 2026-02-27 |
| Louisiana LNG (foundation, 3 trains)Woodside Energy · LNG project cost incl. EPC, owner's cost and contingency (~$960/t); $17.5B incl. pipeline and reserve | LNG plants and terminals | United States | 16.5 Mtpa | USD 15,900M | $17,800M | 2025-11-05 |
| US Energy Corp gas processing facilityU.S. Energy Corp. · capital cost estimate | Gas processing plants | United States | 17 MMcf/d | USD 15M | $17M | 2025-05-12 |
| Rio Grande LNG Phase 1 (3 trains)TotalEnergies · capex of first phase as stated by TotalEnergies | LNG plants and terminals | United States | 17.5 Mtpa | USD 14,800M | $16,844M | 2023-08-01 |
| Southeast Gateway offshore gas pipeline (715 km)TC Energy · 1.3 Bcf/d; estimated cost at FID | Oil and gas pipelines | Mexico | Not stated | USD 4,500M | $5,159M | 2022-11-09 |
| Woodfibre LNGEnbridge · total project cost, liquefaction and floating storage | LNG plants and terminals | Canada | Not stated | USD 5,100M | $5,730M | 2022-07-29 |
| KRIA tranche 2 shallow-cut gas plantPembina Pipeline · includes associated infrastructure | Gas processing plants | Canada | 100 MMcf/d | CAD 165M | $198M | 2020-02-28 |
| Port Arthur refinery coker and sulfur recovery unitValero Energy · board-approved total cost | Refineries and renewable fuels | United States | 55,000 bpd | USD 975M | $1,521M | 2018-10-25 |
| Driftwood LNG (full plant)Tellurian · guaranteed lump-sum turnkey EPC contract with Bechtel | LNG plants and terminals | United States | 27.6 Mtpa | USD 15,200M | $23,912M | 2018-08-08 |
| Duvernay I shallow-cut gas plantPembina Pipeline · gross, incl. supporting infrastructure | Gas processing plants | Canada | 100 MMcf/d | CAD 125M | $166M | 2017-05-05 |
| Wood Buffalo ExtensionEnbridge · definitive cost estimate before optimization | Oil and gas pipelines | Canada | Not stated | CAD 1,800M | $2,418M | 2015-07-31 |
| RIO Pipeline (107 miles)Delek US · estimated total project cost | Oil and gas pipelines | United States | 55,000 bpd | USD 125M | $215M | 2015-07-01 |
| Sabine Pass Liquefaction Stage 2 (Trains 3-4)Cheniere Energy · EPC contract value | LNG plants and terminals | United States | Not stated | USD 4,103M | $7,149M | 2015-04-08 |
| Sabine Pass Liquefaction Trains 5-6Cheniere Energy · capex estimate before FID | LNG plants and terminals | United States | Not stated | USD 6,000M | $9,798M | 2014-04-07 |
| Saturn II NGL extraction facilityPembina Pipeline · expected cost | Gas processing plants | Canada | 200 MMcf/d | CAD 170M | $254M | 2014-02-27 |
| Southern Access (Line 61) expansion to 1.2 million bpdEnbridge Energy Management · estimated cost incl. tankage | Oil and gas pipelines | United States | Not stated | USD 1,250M | $2,063M | 2014-02-18 |
| Norlite diluent pipelineEnbridge · estimated cost | Oil and gas pipelines | Canada | 270,000 bpd | CAD 1,400M | $2,278M | 2013-11-06 |
| Lake Charles ethane crackerSasol · estimated US$5-7 billion (midpoint shown); 1.5 Mt/yr ethylene | Petrochemical plants | United States | 1.5 Mtpa | USD 6,000M | $9,957M | 2013-06-07 |
| Woodland Pipeline Extension (385 km, 36-inch)Enbridge · estimated C$1.0-1.4 billion (low end shown) | Oil and gas pipelines | Canada | 400,000 bpd | CAD 1,000M | $1,610M | 2013-05-08 |
| Line 78, 76-mile 36-inch twin, Flanagan to GriffithEnbridge Energy Management · estimated cost | Oil and gas pipelines | United States | Not stated | USD 495M | $818M | 2013-02-15 |
| Athabasca Pipeline twin (345 km, 36-inch)Enbridge · estimated cost | Oil and gas pipelines | Canada | Not stated | CAD 1,200M | $2,003M | 2012-08-02 |
| Flanagan South PipelineEnbridge · revised estimate (was US$1.9B before upsizing) | Oil and gas pipelines | United States | 585,000 bpd | USD 2,800M | $4,642M | 2012-05-09 |
| Wood River refinery Coker and Refinery Expansion (CORE)Cenovus Energy · total capital cost at completion, gross | Refineries and renewable fuels | United States | Not stated | USD 3,800M | $6,300M | 2012-03-20 |
Mines
458 mine projects with an initial capital figure, from technical report summaries (S-K 1300) and study results filed with the SEC, including Canadian and Australian companies that file there. 306 state a throughput. These are company study estimates, not as-built costs. Countries: Not stated 256, Canada 63, United States 61, Mexico 25, Argentina 9, Chile 9, Brazil 6, Australia 4, Ghana 4, Ecuador 3, Guatemala 3, Peru 3, Tanzania 2, Senegal 2. Commodities: gold 269, copper 42, silver 37, uranium 23, lithium 21, not stated 10, rare earth 8, graphite 6, diamond 6, zinc 5.
Download the mine records (CSV) · API
| Project | Commodity · method | Country | Study · filed | Throughput | Initial capital (today, USD) |
|---|---|---|---|---|---|
| PitarrillaENDEAVOUR SILVER CORP | silver · underground | Mexico | FS · 2026-11-19 | 4,000 t/day | $585MUSD 585M as filed |
| Albany GraphiteZentek Ltd. | graphite · open pit | Canada | PEA · 2026-11-17 | — | $817MUSD 817M as filed |
| BoumadineAya Gold & Silver Inc. | lead · underground | — | PEA · 2026-11-17 | 8,000 t/day | $463MUSD 463M as filed |
| WarintzaSolaris Resources Inc. | gold · underground | Ecuador | FS · 2026-11-13 | — | $3,700MUSD 3,700M as filed |
| Assessment ProcessCanagold Resources Ltd. | gold · underground | Canada | FS · 2026-11-13 | — | $250MUSD 250M as filed |
| MossGold X2 Mining Inc. | gold · open pit | — | PEA · 2026-11-13 | — | $1,441MCAD 2,001M as filed |
| GunnisonGunnison Copper Corp. | copper · open pit | United States | PEA · 2026-11-13 | 2,449 t/day | $1,556MUSD 1,555.6M as filed |
| TransparencyIntegra Resources Corp. | gold · open pit | United States | FS · 2026-11-12 | — | $389MUSD 389M as filed |
| NussirBlue Moon Metals Inc. | copper · underground | — | FS · 2026-11-12 | 6,000 t/day | $184MUSD 184M as filed |
| QueenswayNew Found Gold Corp. | gold · open pit + underground | Canada | PEA · 2026-11-12 | 12,000 t/day | $150MUSD 149.8M as filed |
| ArrowNexGen Energy Ltd. | uranium · underground | Canada | FS · 2026-11-10 | 1,300 t/day | $936MCAD 1,300M as filed |
| Grey FoxMcEwen Inc. | — · underground | — | PFS · 2026-11-09 | — | $181MUSD 180.8M as filed |
| South RailroadEquinox Gold Corp. | gold · underground | United States | Study · 2026-11-09 | 3,698 t/day | $436MUSD 436M as filed |
| GoldrushBARRICK MINING CORP | copper · underground | United States | Study · 2026-11-09 | 38,356 t/day | $1,000MUSD 1,000M as filed |
| Los ReyesTorex Resources Inc. | gold · underground | — | PEA · 2026-11-06 | 5,000 t/day | $515MUSD 514.8M as filed |
| Wheeler RiverDENISON MINES CORP. | uranium · underground | Canada | Study · 2026-11-05 | — | $419MUSD 419.4M as filed |
| EvaHARMONY GOLD MINING CO LTD | gold · — | Australia | FS · 2026-10-30 | 49,315 t/day | $222MUSD 222M as filed |
| Lynn LakeALAMOS GOLD INC | gold · underground | Canada | Study · 2026-10-29 | 2,000 t/day | $937MUSD 937M as filed |
| FranklinSTANDARD LITHIUM LTD. | lithium · — | United States | PEA · 2026-10-20 | — | $3,496MUSD 3,496M as filed |
| ConverseSSR MINING INC. | gold · — | — | PEA · 2026-10-13 | — | $900MUSD 900M as filed |
| ElkNIOCORP DEVELOPMENTS LTD | scandium · underground | Canada | PFS · 2026-09-25 | 3,047 t/day | $1,852MUSD 1,849M as filed |
| AlbanyZentek Ltd. | graphite · open pit | — | PFS · 2026-09-24 | 2,703 t/day | $818MUSD 817M as filed |
| Santa CruzIvanhoe Electric Inc. | copper · underground | United States | FS · 2026-09-23 | 20,000 t/day | $1,432MUSD 1,430M as filed |
| CarangasNEW PACIFIC METALS CORP | silver · open pit | Canada | PFS · 2026-09-23 | 22,000 t/day | $646MUSD 644.5M as filed |
| Pilot Mountain TungstenGuardian Metal Resources PLC | tungsten · — | United States | Study · 2026-09-17 | 4,000 t/day | $289MUSD 288.7M as filed |
| South West ArkansasSTANDARD LITHIUM LTD. | lithium · — | — | DFS · 2026-09-08 | — | $3,506MUSD 3,500M as filed |
| Life-of-mineGold X2 Mining Inc. | gold · open pit | Canada | PEA · 2026-08-27 | 30,137 t/day | $1,480MCAD 2,001M as filed |
| KatanningOceanaGold Corp | gold · open pit | Australia | DFS · 2026-08-17 | 9,863 t/day | $256MAUD 355M as filed |
| Johnson TractContango Silver & Gold Inc. | gold · underground | Canada | IA · 2026-08-14 | 6,849 t/day | $219MUSD 213.6M as filed |
| DeLamarIntegra Resources Corp. | gold · open pit | United States | FS · 2026-08-11 | 27,000 t/day | $400MUSD 389M as filed |
| MesquiteEquinox Gold Corp. | gold · open pit | — | Study · 2026-08-05 | 12,700 t/day | $448MUSD 436M as filed |
| Young-DavidsonALAMOS GOLD INC | gold · underground | Mexico | FS · 2026-07-30 | 20,000 t/day | $172MUSD 165M as filed |
| Kabanga NickelLifezone Metals Ltd | nickel · underground | Tanzania | FS · 2026-07-29 | 9,315 t/day | $981MUSD 942M as filed |
| BrookRamaco Resources, Inc. | coal · — | United States | Study · 2026-07-29 | 7,205 t/day | $3,332MUSD 3,200M as filed |
| JorgeGoldMining Inc. | gold · open pit | Brazil | PFS · 2026-07-22 | 5,500 t/day | $210MUSD 202M as filed |
| Cerro PrietoGoldgroup Mining Inc. | gold · open pit | — | PFS · 2026-07-20 | 4,000 t/day | $16MUSD 15.5M as filed |
| Grassy MountainParamount Gold Nevada Corp. | gold · underground | United States | FS · 2026-07-14 | 1,089 t/day | $198MUSD 189.8M as filed |
| Diamba SudFORTUNA MINING CORP. | gold · open pit | Senegal | FS · 2026-07-13 | 6,849 t/day | $414MUSD 397.5M as filed |
| HammerdownNew Found Gold Corp. | gold · open pit | Canada | PEA · 2026-07-06 | 1,400 t/day | $161MUSD 155M as filed |
| Chaarat ZAAVSILVERCORP METALS INC | gold · underground | — | Study · 2026-06-30 | 5,000 t/day | $19MUSD 18.1M as filed |
| El DomoSILVERCORP METALS INC | — · — | Ecuador | Study · 2026-06-29 | — | $297MUSD 283.7M as filed |
| SleeperParamount Gold Nevada Corp. | gold · open pit | — | FS · 2026-06-23 | 30,000 t/day | $211MUSD 201M as filed |
| MozParamount Gold Nevada Corp. | gold · open pit | — | PFS · 2026-06-23 | — | $211MUSD 201M as filed |
| McIlvenna BayELDORADO GOLD CORP /FI | copper · underground | — | PFS · 2026-06-11 | 4,900 t/day | $1,034MUSD 987.4M as filed |
| Hill Rare EarthCrown PropTech Acquisitions | rare earth · — | — | DFS · 2026-06-10 | — | $341MUSD 325.5M as filed |
| La MinaGoldMining Inc. | gold · open pit | Colombia | PFS · 2026-06-08 | 15,000 t/day | $548MUSD 523M as filed |
| HycroftHYCROFT MINING HOLDING CORP | gold · open pit + underground | United States | PFS · 2026-06-02 | 51,801 t/day | $2,513MUSD 2,400M as filed |
| Hope BayAGNICO EAGLE MINES LTD | gold · underground | — | PEA · 2026-05-19 | 6,000 t/day | $2,480MUSD 2,400M as filed |
| IntegratedDENISON MINES CORP. | uranium · underground | — | PFS · 2026-05-14 | — | $620MUSD 600M as filed |
| Courageous LakeSEABRIDGE GOLD INC | gold · open pit | Canada | PFS · 2026-05-13 | 7,500 t/day | $1,572MUSD 1,522M as filed |
| SunshineSunshine Silver Mining & Refining Co | silver · underground | United States | IA · 2026-05-11 | 907 t/day | $296MUSD 286.9M as filed |
| La Colorada SkarnPAN AMERICAN SILVER CORP | silver · underground | — | PEA · 2026-05-07 | 15,000 t/day | $1,963MUSD 1,900M as filed |
| Eagle MountainMako Mining Corp. | gold · open pit | — | PFS · 2026-04-29 | 5,000 t/day | $101MUSD 95.6M as filed |
| Whistler Gold-CopperU.S. GoldMining Inc. | gold · open pit | United States | IA · 2026-04-17 | 40,000 t/day | $1,353MUSD 1,278.6M as filed |
| Fenn-GibMAYFAIR GOLD CORP. | gold · open pit | — | PFS · 2026-04-14 | 4,800 t/day | $476MUSD 450M as filed |
| ZgounderAya Gold & Silver Inc. | silver · open pit | — | PEA · 2026-04-13 | 3,326 t/day | $472MUSD 446M as filed |
| RobustAya Gold & Silver Inc. | gold · open pit | — | PEA · 2026-04-13 | 8,000 t/day | $472MUSD 446M as filed |
| TerroneraENDEAVOUR SILVER CORP | gold · underground | Mexico | Study · 2026-04-13 | 2,000 t/day | $243MUSD 230M as filed |
| SolidU.S. GOLD CORP. | gold · open pit | — | FS · 2026-04-03 | — | $417MUSD 394M as filed |
| Eau ClaireFURY GOLD MINES LTD | gold · underground | — | PEA · 2026-03-31 | — | $234MUSD 217M as filed |
| EskaySkeena Resources Ltd | gold · open pit | — | DFS · 2026-03-31 | 8,219 t/day | $553MCAD 713M as filed |
| ValentineEquinox Gold Corp. | gold · open pit | Canada | PFS · 2026-03-30 | — | $446MUSD 414M as filed |
| Government PermitsOsisko Development Corp. | gold · underground | — | Study · 2026-03-30 | — | $949MUSD 881M as filed |
| Phoenix ISR UraniumDENISON MINES CORP. | uranium · — | Canada | FS · 2026-03-30 | — | $646MUSD 600M as filed |
| Furnas Copper-GoldEro Copper Corp. | gold · underground | — | PEA · 2026-03-30 | 36,986 t/day | $1,400MUSD 1,300M as filed |
| AvinoAVINO SILVER & GOLD MINES LTD | gold · — | Mexico | Study · 2026-03-27 | 2,250 t/day | $53MUSD 49.1M as filed |
| QiqavikALAMOS GOLD INC | gold · underground | Canada | FS · 2026-03-26 | 9,000 t/day | $178MUSD 165M as filed |
| ArthurAngloGold Ashanti PLC | gold · open pit | United States | PFS · 2026-03-26 | 34,247 t/day | $4,765MUSD 4,424M as filed |
| InfrastructureWestern Copper & Gold Corp | gold · open pit | Argentina | PFS · 2026-03-26 | 120,000 t/day | $3,899MUSD 3,620M as filed |
| La Yaqui GrandeALAMOS GOLD INC | gold · open pit + underground | Canada | Study · 2026-03-26 | 11,900 t/day | $178MUSD 165M as filed |
| Concept The QueenswayNew Found Gold Corp. | gold · open pit + underground | — | PFS · 2026-03-25 | 700 t/day | $167MUSD 154.8M as filed |
| LostUR-ENERGY INC | uranium · — | — | IA · 2026-03-12 | — | $50MUSD 46.5M as filed |
| KemessCenterra Gold Inc. | gold · open pit + underground | Canada | Study · 2026-03-10 | 50,000 t/day | $103MUSD 96M as filed |
| Blackwater Project HemiPERPETUA RESOURCES CORP. | antimony · open pit | — | FS · 2026-02-23 | — | $2,446MUSD 2,215M as filed |
| Camino RojoOrla Mining Ltd. | gold · underground | Mexico | FS · 2026-02-20 | 8,000 t/day | $671MUSD 608.1M as filed |
| Milligan PFS OutlinesCenterra Gold Inc. | gold · open pit + underground | — | PFS · 2026-02-19 | 66,300 t/day | $278MUSD 252M as filed |
| Taxes Lyon CountyLION COPPER & GOLD CORP. | copper · — | — | PFS · 2026-02-18 | — | $799MUSD 724M as filed |
| OdysseyAGNICO EAGLE MINES LTD | gold · underground | — | Study · 2026-02-13 | 20,000 t/day | $298MUSD 270M as filed |
| DonlinNOVAGOLD RESOURCES INC | gold · open pit | United States | PFS · 2026-01-22 | 53,500 t/day | $10,338MUSD 9,233M as filed |
| Execution-ReadyOrla Mining Ltd. | gold · — | — | FS · 2026-01-21 | — | $213MUSD 190M as filed |
| ExtendedKINROSS GOLD CORP | gold · underground | — | Study · 2026-01-15 | 4,800 t/day | $448MUSD 400M as filed |
| Era DoradaAura Minerals Inc. | gold · underground | Guatemala | FS · 2026-01-05 | 1,600 t/day | $428MUSD 382.1M as filed |
| Flagship PhoenixDENISON MINES CORP. | lead · — | — | FS · 2026-01-02 | — | $672MUSD 600M as filed |
| Florida CanyonIntegra Resources Corp. | gold · open pit | United States | PFS · 2025-12-18 | 2,500 t/day | $439MUSD 389M as filed |
| Kilbourne GraphiteTitan Mining Corp | graphite · open pit | — | Study · 2025-12-15 | — | $176MUSD 155.8M as filed |
| After-taxAura Minerals Inc. | gold · underground | Guatemala | FS · 2025-12-08 | — | $431MUSD 382M as filed |
| EstimateNew Found Gold Corp. | copper · — | — | FS · 2025-11-21 | — | $84MUSD 75M as filed |
| PanucoVizsla Silver Corp. | gold · underground | Canada | FS · 2025-11-19 | 3,288 t/day | $267MUSD 238.7M as filed |
| SpringpoleFirst Mining Gold Corp. | gold · open pit | Canada | FS · 2025-11-18 | 30,000 t/day | $390MUSD 348.6M as filed |
| Environmental ApprovalLithium Argentina AG | lithium · — | Argentina | Study · 2025-11-14 | — | $1,232MUSD 1,100M as filed |
| Kindersley LithiumDENISON MINES CORP. | lithium · underground | — | PEA · 2025-11-07 | — | $470MUSD 419.4M as filed |
| Rhyolite Ridge Lithium-Boronioneer Ltd | lithium · — | — | Study · 2025-10-29 | 8,219 t/day | $17MUSD 15M as filed |
| ToroparuAris Mining Corp | gold · open pit | — | PFS · 2025-10-29 | 19,178 t/day | $923MUSD 820M as filed |
| Tonopah FlatsAMERICAN BATTERY TECHNOLOGY Co | lithium · open pit | — | Study · 2025-10-16 | 33,973 t/day | $231MUSD 205.6M as filed |
| Advances Diamba SudFORTUNA MINING CORP. | gold · open pit | — | DFS · 2025-10-15 | 6,849 t/day | $319MUSD 283.2M as filed |
| Confirms Economically RobustMcEwen Inc. | copper · — | Argentina | FS · 2025-10-09 | — | $3,567MUSD 3,170M as filed |
| EwoyaaSayona Mining Ltd | lithium · open pit | Ghana | DFS · 2025-09-16 | — | $303MUSD 270M as filed |
| High-GradeAris Mining Corp | gold · underground | — | PFS · 2025-09-03 | 3,500 t/day | $702MUSD 625M as filed |
| MatawinieNouveau Monde Graphite Inc. | graphite · open pit | — | FS · 2025-08-11 | — | $467MUSD 415M as filed |
| OptimizedNew Found Gold Corp. | gold · open pit + underground | — | Study · 2025-08-08 | 700 t/day | $174MUSD 155M as filed |
| GryphonDENISON MINES CORP. | uranium · underground | Canada | PFS · 2025-08-08 | — | $286MUSD 254M as filed |
| Fort Cady5E Advanced Materials, Inc. | boron · — | — | DFS · 2025-08-07 | — | $413MUSD 367M as filed |
| YellowheadTASEKO MINES LTD | copper · open pit | Canada | Study · 2025-08-07 | 90,000 t/day | $261MUSD 232M as filed |
| GoldfieldCenterra Gold Inc. | gold · open pit | — | Study · 2025-08-06 | — | $283MUSD 252M as filed |
| IndicativeDENISON MINES CORP. | uranium · — | — | PEA · 2025-08-06 | — | $286MUSD 254M as filed |
| YeringtonLION COPPER & GOLD CORP. | copper · open pit | — | PFS · 2025-08-06 | 41,096 t/day | $814MUSD 724M as filed |
| LocalNexGen Energy Ltd. | uranium · — | — | FS · 2025-08-06 | — | $1,461MUSD 1,300M as filed |
| IslandALAMOS GOLD INC | gold · underground | Mexico | FS · 2025-07-31 | 20,000 t/day | $75MUSD 67M as filed |
| Well-DefinedVISTA GOLD CORP | gold · — | Australia | FS · 2025-07-29 | 15,000 t/day | $478MUSD 425M as filed |
| NorthLifezone Metals Ltd | nickel · underground | Tanzania | FS · 2025-07-18 | 9,315 t/day | $1,061MUSD 943M as filed |
| GramaloteB2GOLD CORP | gold · open pit | Colombia | FS · 2025-07-14 | 97,000 t/day | $833MUSD 740M as filed |
| Rare EarthRamaco Resources, Inc. | rare earth · — | — | PEA · 2025-07-10 | — | $651MUSD 579M as filed |
| GibraltarTASEKO MINES LTD | copper · open pit | Canada | PFS · 2025-07-10 | 90,000 t/day | $2,250MUSD 2,000M as filed |
| WharfDakota Gold Corp. | gold · open pit | United States | FS · 2025-07-07 | 7,000 t/day | $432MUSD 384M as filed |
| Rhyolite Ridgeioneer Ltd | lithium · — | — | FS · 2025-06-13 | — | $1,882MUSD 1,667.9M as filed |
| CaribooOsisko Development Corp. | gold · underground | Canada | FS · 2025-06-12 | 4,900 t/day | $994MUSD 881M as filed |
| ErnestoAura Minerals Inc. | gold · — | Brazil | FS · 2025-06-09 | 3,562 t/day | $121MUSD 107M as filed |
| BullfrogENERGY FUELS INC | uranium · underground | — | PFS · 2025-06-03 | — | $62MUSD 55M as filed |
| WildcatIntegra Resources Corp. | gold · open pit | United States | PEA · 2025-05-14 | — | $130MUSD 115M as filed |
| ThompsonCenterra Gold Inc. | molybdenum · open pit | — | PFS · 2025-05-06 | 52,575 t/day | $450MUSD 397M as filed |
The newest 120 are shown; the CSV holds all 458.
Airport runways
411 FAA grants for rehabilitating or reconstructing the only paved runway at an airport, divided by the runway’s area from FAA records. Rehabilitation: $3.64–$83.48 per sq yd (median $15.28, 303 grants). Reconstruction: $3.98–$184.42 (median $24.59, 108 grants). Grants carry the federal share only.
Power generation
Published averages from EIA Form EIA-860, generators installed in 2024, today’s prices: Solar $2,151/kW · Battery storage $1,694/kW · Wind $2,170/kW · Natural gas $1,158/kW · Petroleum liquids $1,229/kW. Grants and tax credits are excluded by EIA.
Stadiums, data centres and offshore platforms
11 large projects with a published cost, each from a public owner, state body or company filing. Stadium costs are final or at completion; data centre and offshore costs are announced or set at the investment decision, and are labelled so. Older costs are moved to today’s prices with the named BLS price index.
| Project | Place | Cost (year) | Today | Basis | Source |
|---|---|---|---|---|---|
| U.S. Bank Stadium | Minneapolis, Minnesota | $1,100M (2016) | $1,962M | Total cost as published by the venue (owner: Minnesota Sports Facilities Authority) | U.S. Bank Stadium (Minnesota Sports Facilities Authority), 2018-01 |
| Mercedes-Benz Stadium | Atlanta, Georgia | $1,500M (2017) | $2,616M | Construction value stated by the builder at a Georgia state board meeting (owner: Georgia World Congress Center Authority) | Georgia State Workforce Development Board, 2017-11-09 |
| Allegiant Stadium | Las Vegas, Nevada | $1,970M (2020) | $3,078M | Final building construction cost (Las Vegas Stadium Authority) | Las Vegas Stadium Authority, 2020-09-17 |
| Highmark Stadium | Orchard Park, New York | $2,100M (2026) | $2,100M | Cost at completion announced by New York State | Office of the Governor of New York, 2026-06-23 |
| New Nissan Stadium (under construction) | Nashville, Tennessee | $2,230M (2026) | $2,230M | Estimated total construction cost in a city internal audit; not final, not used in the per-seat band | Metropolitan Nashville Office of Internal Audit, 2026-06-10 |
| Polaris Forge 1 (Applied Digital) | Ellendale, North Dakota | $4,800M (2026) | $4,800M | Company's anticipated capex of $11M to $13M per MW of critical IT load, 400 MW (SEC filing); midpoint shown | U.S. Securities and Exchange Commission (Applied Digital filing), 2026-04 |
| Vantage VA4 campus | Stafford County, Virginia | $2,000M (2025) | $2,000M | Investment announced by the Governor of Virginia; three buildings, 929,000 sq ft, 192 MW | Office of the Governor of Virginia (as reported by Potomac Local), 2025-11-06 |
| Meta data centre campus | Beaver Dam, Wisconsin | $1,000M (2025) | $1,000M | Investment of more than $1 billion announced with the state economic development agency; over 700,000 sq ft | Wisconsin Economic Development Corporation, 2025-11-12 |
| AVAIO Digital Taurus campus | Brandon, Mississippi | $6,000M (2025) | $6,000M | Investment announced by the Governor of Mississippi; size not stated | Office of the Governor of Mississippi, 2025-08-19 |
| Mad Dog Phase 2 (Argos platform), bp | Gulf of America, offshore Louisiana | $9,000M (2016) | $11,668M | Cost at final investment decision announced by the company; up to 140,000 barrels of oil a day | bp (company announcement), 2016-12 |
| Anchor, Chevron | Gulf of America, offshore Louisiana | $5,700M (2019) | $6,894M | Cost at final investment decision announced by the company; 75,000 barrels of oil a day | Chevron (company announcement), 2019-12 |
Per unit, today’s prices, lowest to highest: stadiums $29,544–$47,354 per seat (4 records); data centres $10.4M–$13.0M per MW of IT load; offshore platforms $83,340–$91,919 per barrel a day of capacity. Few records: these are not statistical bands.
Highway pay-item bands from PDF bid tabs
Four state DOTs publish their bid tabulations only as PDFs. We read each PDF with pdftotext and keep the low bidder’s unit price for every pay item let since 2024-11-22. A band is published only with 20 or more low bids from 10 or more letting dates in one quantity range, and when the high (p90) is no more than 15 times the low (p10). These sit beside the Texas and Oregon bands, which come as data. Lump sums, dollar items and estimates are left out.
| Publisher | PDFs read | Contracts | Low-bid lines | Letting dates | Bands published |
|---|---|---|---|---|---|
| Washington State DOT | 137 | 117 | 4,003 | 58, 2025-01-29 to 2026-11-18 | 1 |
| Connecticut DOT | 204 | 139 | 11,518 | 68, 2024-12-04 to 2026-10-28 | 7 |
| Indiana DOT | 32 | 699 | 48,675 | 26, 2024-12-11 to 2026-09-09 | 396 |
| New Jersey DOT | 99 | 99 | 6,665 | 57, 2025-07-10 to 2026-06-23 | 1 |
Indiana prints dozens of contracts in each monthly letting, so most of its common items reach the bar. Connecticut, New Jersey and Washington let fewer contracts with the same item at the same size, so few of their items qualify yet. Washington tabs give line numbers, not item codes, so its bands match on the exact item name. New York’s bid tab site asks automated readers to stay out (robots.txt), so it is not read.
Washington State DOT: 1 published band
Connecticut DOT: 7 published bands
| Item | Quantity | Low · median · high | Bids | Source PDFs |
|---|---|---|---|---|
| 0969062CONSTRUCTION FIELD OFFICE, MEDIUM | 8 to under 16 MO. | $3,886.5 · $5,012.5 · $6,510 | 46 from 32 lettings | 0172-0540, 0171-0512 and 42 more |
| 0978002TRAFFIC DRUM | 128 to under 256 EA. | $7.4 · $75 · $92.6 | 29 from 27 lettings | 0172-0540, 0170-3736 and 27 more |
| 0979003CONSTRUCTION BARRICADE TYPE III | 8 to under 16 EA. | $150 · $172.5 · $245.1 | 22 from 17 lettings | 0170-3736, 0173-0548 and 20 more |
| 098110042'' TRAFFIC CONE | 128 to under 256 EA. | $40 · $43.75 · $59 | 21 from 20 lettings | 0172-0540, 0171-0512 and 19 more |
| 1220027CONSTRUCTION SIGNS | 512 to under 1,024 S.F. | $10 · $23.78 · $42.5 | 36 from 31 lettings | 0171-0512, 0170-3737 and 34 more |
| 1220027CONSTRUCTION SIGNS | 256 to under 512 S.F. | $7.78 · $25 · $40 | 30 from 27 lettings | 0172-0540, 0046-0131-R1 and 28 more |
| 0969062CONSTRUCTION FIELD OFFICE, MEDIUM | 16 to under 32 MO. | $3,200 · $4,800 · $5,460 | 35 from 29 lettings | 0053-0196, 0094-0264 and 31 more |
Indiana DOT: 396 published bands
| Item | Quantity | Low · median · high | Bids | Source PDFs |
|---|---|---|---|---|
| 107-09367INSPECTION HOLE, 3 FT DEEP OR LESS | 2 to under 4 EACH | $195 · $760 · $1,682 | 20 from 12 lettings | B -39043-A, B -43226-A and 10 more |
| 202-02240PAVEMENT REMOVAL | 512 to under 1,024 SYS | $20.07 · $50 · $60 | 33 from 17 lettings | B -39043-A, B -42175-A and 15 more |
| 203-02000EXCAVATION, COMMON | 256 to under 512 CYS | $30 · $64.13 · $93.8 | 59 from 16 lettings | B -39043-A, B -42795-A and 14 more |
| 207-09935SUBGRADE TREATMENT, TYPE IC | 1,024 to under 2,048 SYS | $30 · $40 · $55.9 | 72 from 19 lettings | B -39043-A, B -39418-B and 17 more |
| 214-12239GEOTEXTILE FOR PAVEMENT, TYPE 2B | 1,024 to under 2,048 SYS | $3.29 · $5 · $7.91 | 44 from 17 lettings | B -39043-A, B -42175-A and 15 more |
| 301-12234COMPACTED AGGREGATE, NO. 53 | 64 to under 128 CYS | $57.8 · $92.43 · $158 | 27 from 13 lettings | B -39043-A, B -42829-A and 11 more |
| 302-06464SUBBASE FOR PCCP | 64 to under 128 CYS | $103.07 · $150 · $211.5 | 50 from 18 lettings | B -39043-A, B -42829-A and 16 more |
| 303-01180COMPACTED AGGREGATE, NO. 53 | 64 to under 128 TON | $45 · $68 · $110 | 63 from 19 lettings | B -39043-A, B -42829-A and 17 more |
| 306-08034MILLING, ASPHALT, 1 1/2 IN. | 1,024 to under 2,048 SYS | $3.5 · $6.5 · $13.25 | 31 from 16 lettings | B -39043-A, R -44764-A and 14 more |
| 401-000005QC/QA-HMA, 3, 58H, SURFACE, 9.5 mm | 128 to under 256 TON | $131.75 · $182.5 · $243 | 26 from 16 lettings | B -39043-A, B -42240-A and 14 more |
| 401-000047QC/QA-HMA, 3, 58S, BASE, 25.0 mm | 256 to under 512 TON | $104.36 · $128.5 · $175.4 | 42 from 16 lettings | B -39043-A, B -39418-B and 14 more |
| 601-02241GUARDRAIL, REMOVE | 512 to under 1,024 LFT | $2 · $5 · $9.4 | 63 from 18 lettings | B -39043-A, B -42175-A and 16 more |
| 601-12281GUARDRAIL, MGS W-BEAM, 6 FT 3 IN. SPACING | 128 to under 256 LFT | $19 · $22 · $26.1 | 40 from 15 lettings | B -39043-A, B -43340-A and 13 more |
| 601-12289GUARDRAIL HEIGHT TRANSITION, MGS | 2 to under 4 EACH | $850 · $950 · $1,360 | 35 from 17 lettings | B -39043-A, B -42174-A and 15 more |
| 601-12292GUARDRAIL TRANSITION, MGS WITHOUT CURB | 4 to under 8 EACH | $2,850 · $3,275 · $3,700 | 73 from 18 lettings | B -39043-A, B -42175-A and 16 more |
| 601-94689GUARDRAIL END TREATMENT, TYPE OS | 1 to under 2 EACH | $2,445 · $3,125 · $3,705 | 47 from 16 lettings | B -39043-A, B -42174-A and 14 more |
| 609-06259REINFORCED CONCRETE BRIDGE APPROACH, 12 IN. | 256 to under 512 SYS | $153.5 · $200 · $264.5 | 52 from 18 lettings | B -39043-A, B -42829-A and 16 more |
| 616-06405RIPRAP, REVETMENT | 256 to under 512 TON | $58.1 · $87.8 · $149 | 62 from 20 lettings | B -39043-A, B -42842-A and 18 more |
| 621-01004MOBILIZATION AND DEMOBILIZATION FOR SEEDING | 2 to under 4 EACH | $214 · $500 · $1,000 | 196 from 21 lettings | B -39043-A, B -39418-B and 19 more |
| 621-02770EROSION CONTROL BLANKET | 512 to under 1,024 SYS | $2.2 · $2.75 · $5 | 31 from 15 lettings | B -39043-A, R -43004-A and 13 more |
| 628-09403FIELD OFFICE, TYPE C | 8 to under 16 MOS | $1,330.52 · $3,000 · $4,144 | 139 from 21 lettings | B -39043-A, B -42240-A and 19 more |
| 628-11976COMPUTER SYSTEM EQUIPMENT | 2 to under 4 EACH | $207.5 · $750 · $1,500 | 196 from 21 lettings | B -39043-A, B -39418-B and 19 more |
| 703-06029REINFORCING BARS, EPOXY COATED | 16,384 to under 32,768 LBS | $1.46 · $2 · $2.32 | 27 from 15 lettings | B -39043-A, B -43418-A and 13 more |
| 706-11620CONCRETE BRIDGE RAILING TRANSITION, TYPE TFC | 4 to under 8 EACH | $1,523.55 · $2,687.26 · $5,000 | 66 from 17 lettings | B -39043-A, B -42832-A and 15 more |
| 722-01066HYDRODEMOLITION | 1,024 to under 2,048 SYS | $68.5 · $75 · $126.5 | 28 from 13 lettings | B -39043-A, B -42175-A and 11 more |
New Jersey DOT: 1 published band
Every band, contract and source PDF: download the CSV.
Sources
- U.S. Securities and Exchange Commission: EDGAR full-text search and filing archive (S-K 1300 technical report summaries, study-result exhibits) · 458 records
- USAspending.gov (U.S. Treasury): Contract awards, NAICS 236/237, FY2017–FY2026, $500k and up · 28,788 records
- Federal Aviation Administration: Airport Improvement Program grant histories FY2018–FY2026 · 17,995 records
- Federal Aviation Administration: NASR 28-day subscription, runway dimensions (effective 2026-10-29) · size data
- Oregon Department of Transportation: Bid Item Prices, annual bid data 2021–2026 · 33,271 records
- U.S. Energy Information Administration: Construction cost data for electric generators (Form EIA-860), 2013–2024 · 547 published averages
- Ministry of Finance, Singapore: Government Procurement via GeBIZ (data.gov.sg), FY2021–2026 awarded works · 1,241 records
- Hawaii Department of Transportation, Highways Division: Bid Tab Data - Numeric Values (open data), 2014–2026 · 9,129 records
- U.S. Energy Information Administration: U.S. natural gas pipeline projects (October 2026 workbook) · 1,070 records
- U.S. Securities and Exchange Commission: EDGAR filings: LNG, refinery, oil and gas, petrochemical and pipeline project announcements (8-K/6-K exhibits) · 25 records
- U.S. Bureau of Labor Statistics via FRED: PPI series used to move costs to today's prices: PCU236222236222 (buildings), WPUIP2312301 (civil, mines, power) · price index
- Board of Governors of the Federal Reserve System via FRED: Annual average exchange rates DEXCAUS, DEXUSAL, DEXSIUS · exchange rates
Retrieved 2026-11-22 through each publisher’s official API or bulk download, within its rate limits. Accuracy by asset type is on the accuracy page.
Gaps
- Saudi Arabia, Qatar and UAE: no official machine-readable award feed was reachable; Etimad awards are only browsable on the portal, so none are loaded.
- SEDAR+ and ASX: no bulk or API access under their terms; Canadian and Australian studies are included only where the company also filed them with the SEC.
- Minnesota DOT bid history could not be reached from our servers; West Virginia publishes averages only (no contract-level bids).
- Federal award descriptions rarely state a size: per-unit figures exist for a small share of awards.
- Oil and gas: project costs come only from company announcements filed with the SEC and the EIA pipeline workbook; no government series of refinery, LNG or offshore field costs exists, and drilling rig costs are not loaded.
- FERC and utility rate-case filings: not loaded yet (document-by-document PDFs).